Second phase of Londonderry rail upgrade to be finished in 2016

The long-awaited second phase of the Londonderry to Coleraine rail upgrade will be completed in 2016 just, the Rail Minister Danny Kennedy has promised.
ChrisPlayfairChrisPlayfair
ChrisPlayfair

Back in April the Sentinel reported how the start date for work on Phase 2 had slipped from May to September.

But Mr Kennedy has today promised the work will be completed by the end of next year.

Hide Ad
Hide Ad

In a statement he said: “The rail track between Londonderry and Coleraine has suffered for years from underinvestment. The original preference was for a complete relay and signalling to be carried out in a single project.

“However, funding constraints meant that the project could not go ahead at that time. In October 2011 following my intervention we approved carrying out the relay in 3 phases.

“Phase 1 relayed the worst parts of the track and was completed ahead of schedule in March 2013 and within its budget of £26.7m.

“Phase 2 involves the full re-signalling of the Coleraine to Londonderry line section and the addition of a passing loop originally to be completed by the end of 2015 and estimated to cost £19.9m based on analysis at that time.

Hide Ad
Hide Ad

“It was originally envisaged to be a single Design and Build project. However, the initial tender exercise for this procurement produced only one bidder in 2013.

“It was judged that this bid did not represent value for money and carried unacceptable risks that costs could be open ended.

“As a result the procurement strategy for the Phase 2 Signalling and Telecommunications was reviewed. Translink decided to split the project into two distinct packages.

“Passing loop work was separated from the Signalling and would be tendered separately. This delayed the project completion from late 2015 to late 2016.

Hide Ad
Hide Ad

“Following the adoption of this revised procurement strategy a detailed signalling design produced in 2014 suggested that the original cost estimate for the project was seriously underestimated and out of date.

“I expressed my disappointment at this and informed members at the time. I directed my officials to work closely with Translink to resolve this and commissioned an independent Project Assessment Review (PAR) of the project at that stage.

“The review confirmed that the current supplier base in the UK for this type of project is very overstretched and those companies who may have been expected to bid for this project are already heavily committed in Network Rail projects in Britain.

“This created a clear risk to the procurement process for signalling works in Phase 2.

Hide Ad
Hide Ad

“Translink subsequently prepared and approved a fully-detailed pre-tender estimate, independently assured, prior to the formal commencement of the formal procurement process. This identified a cost of £40m.

“The PAR report had made it clear that due to the scale of the market in Great Britain and the relatively small scale of the Phase 2 project there was a risk that it might not attract sufficient interest from suppliers. There were commercial sensitivities around this and the release of the PAR report which are now resolved.

“Four GB-based firms initially expressed sufficient interest to participate in the Pre-Qualification Questionnaire stage of the process but ultimately only one, Babcock Rail, submitted a tender.

“Translink held robust negotiations with Babcock which ultimately resulted in a best and final offer for the Signalling and Telecomms part of the project that was reduced by over 10% against the initial price submitted.

Hide Ad
Hide Ad

“However, the increased overall project cost of £46.4m creates a difficulty. Prior to the second tender a revised, independently assured estimate of £40.1m was produced. This covered both the Signalling and Passing Loop elements.

“Neither the Translink Accounting Officer nor my Accounting Officer could sign off the bid as representing Value-For-Money (VFM) although they both agreed that the proposed project was the best public policy option.

“As a result I issued a direction to my Permanent Secretary that Translink should proceed to conclude the contract with Babcock. In line with Managing Public Money (NI) this direction was approved by the Minister for Finance.

“I am pleased to inform this Assembly that the contract for the signalling element of Phase 2 is now in place between Translink and Babcock – a well recognised and respected supplier nationally and internationally. This will enable Phase 2 to be substantially completed by December 2016.

Hide Ad
Hide Ad

“At a time of financial constraint this has not been an easy decision, but I believe it is the right one and demonstrates that this Assembly can deliver on its promises to take decisions which will benefit our citizens.

“I believe the investment that has taken place in our railways is tangible proof that we can deliver change and deliver on our promises. Rail passenger journeys continue to grow year on year particularly on the Londonderry line.

“Improvements to our infrastructure create the environment to grow our economy, create tourism opportunities and better connect our two largest cities. I know all members will support me in this.”

DUP MLA Gary Middleton welcomed the announcement.

“It is very welcome news that Phase 2 of the railway line upgrade is now to progress with the estimated completion to be in December 2016.

Hide Ad
Hide Ad

“The rail service in the North West is a vital component of our transport infrastructure. With rail passenger journeys continuing to grow year on year on the Londonderry line, it is clear that this project is in clear demand by members of the public.

“There is no doubt that this project will have a catalytic effect in terms of the local economy, tourism and future jobs and investment. The two largest cities in Northern Ireland will be better connected which will be welcomed by all who travel between them.

“The transport infrastructure in the North West in terms of the A5 and A6 projects are still vital and must also be progressed. I will continue to lobby the DRD Minister in relation to these projects.

“I look forward to seeing the completion of the second phase of the railway project.”

Hide Ad
Hide Ad

Ulster Unionist Foyle representative Julia Kee said: “News that work can get underway on Phase 2 of the Coleraine to Londonderry railway line will be welcomed not only in Londonderry, but also across the North West.

“Improvements to transport infrastructure can bring economic and tourism benefits to the City and I look forward to an increase in the frequency of train services, improving our connectivity to the rest of the country.

“With Londonderry’s economic black spot status, this is welcome news. We hear regularly about job creation from other parties, but this physical regeneration will add much needed infrastructure to the North West.

“It’s a pity Danny couldnt have pushed this decision pre-election. But the UUP are in the frame of mind that we do things for Northern Ireland, the people of Northern Ireland and not for party gain.

Hide Ad
Hide Ad

“Danny’s announcement will be welcomed not least by lobby group Into the West, whom we hope are meeting Minister Kennedy in the not to distant future about the rail links and the Waterside Railway Station in particular.

“The date for this meeting is to be agreed shortly.”