Ballyclare area motorists advised £675,000 resurfacing scheme to take place over a three-month period

Motorists are advised to expect delays during a £675,000 resurfacing scheme on the U60 Ballycorr Road, Ballyclare.

The carriageway and footway project – with a Monday, July 27, commencement date - will extend approximately 0.84km from the junction with C37 Ballyeaston Road to the Craighill Manor junction and take just over three months to complete.

Announcing the scheme, Infrastructure Minister Liz Kimmins said: “This is a substantial investment for the Ballyclare area which will deliver significant benefits for residents and road users. The investment demonstrates my commitment to investing in and improving our road network, which is vital for connecting our businesses and communities.

"This work will greatly improve the strength and surface quality of this section of the road network to the benefit of residents, businesses and those travelling in the Ballyclare area.

General view of the Ballycorr Road, Ballyclare. Image: Googleplaceholder image
General view of the Ballycorr Road, Ballyclare. Image: Google

"Work is expected to be substantially completed by Thursday, 5 November, 2026. I would like to thank residents, local businesses and commuters for their patience while this essential infrastructure work is carried out.”

To facilitate the safe delivery of the scheme, the Department for Infrastructure (DfI) says it will be necessary to implement a road closure, which will be operational from 8am to 6pm, from Monday, July 27 to Friday, August 28.

Thereafter, the start and end times of the closure will be amended to accommodate school traffic, until completion of the scheme by Thursday, November 5.

During the road closure, a signed diversionary route will be in place via: C37 Ballyeaston Road – C37 Ballyeaston Village – C37 Lower Ballyboley Road – U60 Ballycorr Road – C37 Church Road and vice versa.

In a statement, DfI added: “The Department has programmed the work operations and traffic management arrangements to minimise inconvenience however, while steps have been taken to accommodate local access and Translink bus and school services throughout the scheme, road users should expect some delays and are advised to allow additional time when travelling in the vicinity of the works and are asked to comply with all temporary traffic restrictions.

"Subject to favourable weather conditions, the works will be substantially complete by Thursday, November 5, 2026, however the Department will keep the public informed of any change.”