M2 Motorway motorists warned of revised closure plan with £1.5m resurfacing scheme ahead of schedule
A £1.5million resurfacing scheme on the M2 Motorway between junctions 4 and 5 has progressed ahead of schedule and will now be completed this weekend.
And the Department for Infrastructure (DfI) is advising motorists it has therefore brought forward plans to close the M2, to remove the contraflow and allow the central reserve vehicle restraint system (VRS) to be reinstalled, from Sunday night (July 26) to Friday (July 24).
In a statement, DfI added “This now means the M2 Motorway will be totally closed in both directions overnight from 8pm on Friday, 24 July, until 7am on Saturday, 25 July, 2026 between Junction 4 Sandyknowes and Junction 5 Templepatrick.


"A diversionary route will be signed via A6 Antrim Road – A6 Ballyclare Road – A57 Ballyclare Road.
"The road will then be fully reopen to traffic in both directions from Saturday at 7am.
"The Department added it would like to thank road users for their co-operation while these works have taken place.”