NI Water has identified Molesworth Street as one of the highest priority areas for stormwater separation

NI Water will start a six-week programme of work at the end of June to install new stormwater infrastructure in Cookstown.

The installation of dedicated stormwater pipelines and new manholes will remove storm (rain) water from the combined wastewater network, helping to reduce the risk of out-of-sewer flooding in the area, provide more capacity and help support localised development.

The work – which is scheduled to start on Monday, June 29, on Union Street – will require localised lane closures around working areas, initially on a section of Union Street and later on Molesworth Street.

Speaking about the works and the associated traffic management, Robert McLean, NI Water Senior Project Manager said: “The Molesworth Street area has been identified as one of the highest priority areas for stormwater separation in our current programme of works. The scheme will remove over a hectare of drainage from the combined system, reducing pressure on the local network and delivering environmental improvements through reduced spills.

Pictured are the Stormwater Separation Project Team - the work planned for Cookstown is part of a rolling investment programme which has seen £5m invested over the last 3 years. From left are Richard Chambers, AG Wilson (Portadown); Ronan O’Doherty, APP (Associated Pipeline Products Ltd. Lisburn); Robert McLean, NI Water; Jamie Sterritt, AtkinsRéalis; and Niall Mullan, CivCo (Maghera) | Suppliedplaceholder image
Pictured are the Stormwater Separation Project Team - the work planned for Cookstown is part of a rolling investment programme which has seen £5m invested over the last 3 years. From left are Richard Chambers, AG Wilson (Portadown); Ronan O’Doherty, APP (Associated Pipeline Products Ltd. Lisburn); Robert McLean, NI Water; Jamie Sterritt, AtkinsRéalis; and Niall Mullan, CivCo (Maghera) | Supplied
placeholder image
Read More
Cookstown Enterprise Centre developing new facility to drive innovation and comm...

“Pipelaying is scheduled to begin at the Molesworth Street/Union Street junction and will progress along Union Street as far as The Railway Bar over approximately three to four weeks. The second phase of network improvements will take place in the layby area between Molesworth Plaza and Cookstown Hockey Club.

“Localised lane closures will be in place around working areas, with access maintained to residential properties, businesses and car parks. All traffic management will be removed for the contractor’s summer holiday period on Friday, July 10 and will be reinstated on Monday, July 27.

“NI Water said they will do everything to complete the works as quickly as possible and keep disruption to a minimum.